With completion in sight, what’s subsequent for the Trans Mountain pipeline challenge?

5 min read

Article content material

CALGARY — After greater than 4 years of building and a minimum of $34 billion in prices, the Trans Mountain pipeline enlargement challenge is almost full. Right here’s a take a look at what milestones to count on within the coming weeks as the huge pipeline will get prepared to start out transport Canadian oil to the West Coast:

Decision of B.C. building challenges: Crown company Trans Mountain Corp. has been coping with construction-related challenges within the Fraser Valley between Hope and Chilliwack, the place it encountered an “obstruction” when attempting to drag the pipe into the horizontal gap that had been drilled for it. The setback pressured the corporate to take away the pipe briefly to deal with the difficulty, however Trans Mountain Corp. says it’s nearing a decision and expects to have the ability to re-install the pipe in that part throughout the subsequent couple of weeks.

Commercial 2

Article content material

Article content material

Mechanical completion: This marks the ultimate stage of bodily building of the pipeline. As soon as the difficult section of pipe has been efficiently pulled again into its location, Trans Mountain will be capable to full the “remaining weld,” or what’s formally often known as mechanical completion.

Go away To Open: After building is completed however earlier than the pipeline could be put into service, there are a number of regulatory steps that should be accomplished. In accordance with the Canada Vitality Regulator Act, corporations require permission from the CER earlier than commencing operations of a pipeline. This course of known as Go away to Open and requires outcomes from a sequence of inspections and security checks. As a result of the Trans Mountain challenge has been constructed in phases, the corporate has been making use of for Go away to Open permission in levels with the intention to permit flexibility in the course of the commissioning and startup course of.

Line fill: This time period is used to explain the ultimate levels of labor required to organize and finally fill the expanded pipeline system with greater than 4 billion barrels of oil. The method will take a number of weeks to finish. Whereas line fill has not but began on the newly constructed pipe, a part of the Trans Mountain enlargement challenge includes reactivating two older pipeline segments that had been maintained in a deactivated state. Preliminary line fill has already begun in B.C. on that part of the challenge.

Commercial 3

Article content material

In-service: This time period refers to when your entire expanded pipeline system is absolutely operational and able to make common deliveries. In response to a Bloomberg report, China’s Sinochem Group has bought one of many first shipments, a 550,000-barrel cargo from Suncor Vitality Inc., which can load from the Trans Mountain enlargement pipeline in Might-June. Trans Mountain is constant to focus on an in-service date someday within the second quarter of 2024.

Cleanup and reclamation: As soon as the expanded pipeline is operational, required cleanup and reclamation work will proceed within the challenge’s building zone.

This report by The Canadian Press was first revealed March 26, 2024.